Gas Processing & NGL Recovery

Project Value: $50 MM

Responsibilities

  • Project design including DBM, P&ID, detailed engineering, equipment specification
  • Preparation of bid and contract documents including bid evaluation, award and issue of PO's
  • Advanced process control and commissioning
  • Operator training and commissioning
  • Cost control and schedule

Description

  • Removal of acid gases from ethane vapor
  • De-butanizer and butane splitter fractionation
  • Utilities and off-sites